SCB13 dry-type transformers for the Shuchuangyuan industrial park project

Industrial Park Dry-Type Transformers – Shuchuangyuan

Twelve dry-type transformers for Plot No. 8, Phase II of the Bank Card Industrial Park, 2024.

For Plot No. 8, Phase II of the Bank Card Industrial Park (Shuchuangyuan), we supplied twelve cast-resin dry-type transformers. Two 20,000 kVA SCZ13 units handle the 35/10.5 kV main supply, and ten SCB13 units of 1,600 and 2,000 kVA distribute 10/0.4 kV power to the buildings.

Twelve dry-type transformers, from 35 kV main supply to building distribution, for one industrial park.

Scope of Supply

2 × SCZ13-20000/35/10.5, 20,000 kVA, 35/10.5 kV, on-load tap changer
2 × SCB13-1600/10/0.4, 1,600 kVA, 10/0.4 kV
8 × SCB13-2000/10/0.4, 2,000 kVA, 10/0.4 kV

Cast-resin dry-type transformers contain no oil, which makes them suited to indoor substations in commercial and industrial buildings.

How We Deliver Each Project

Every Yuantong project follows the same controlled process, from technical review to delivery.

01

Requirements & Design

We review capacity, voltage, standard and site conditions, then complete the electrical design with computerized design software and 3D structural modelling.
02

Manufacturing

Cores, coils and assemblies are produced in our Hai'an, Jiangsu factory, including silicon steel cutting, coil winding, vacuum casting and drying.
03

Factory Testing

Every unit is tested in our test hall and receives 100% inspection of appearance and function before release.
04

Packing & Delivery

Units are packed in export wooden cases and delivered by road in China or shipped by sea from Shanghai.

Standards & Quality

Our transformers are designed and built to international and Chinese national (GB) standards as specified by the customer. Our management systems are certified to ISO 9001, ISO 14001 and ISO 45001, and our low-voltage products hold CE attestation of conformity under the Low Voltage and EMC directives.

Project Information

Key facts of this project.

Application

Year

2024

Products

Dry-type transformers

Quantity

12 units

Location

China